During risk planning, we decide what we will do if risks occur. During Implement Risk Responses, we actually do.

Key Activities

1. Monitor Risk Triggers

Risk triggers are warning signs indicating a risk may occur.

Example

Risk: Vendor delivery delay

Trigger: Vendor misses intermediate milestone

When the trigger occurs: Response plan must start immediately.

2. Execute Planned Responses

The project team performs predefined actions.

Example

Threat: Key engineer may leave project.

Planned Response: Cross-training.

Implementation: Actually conduct training sessions.

3. Implement Contingency Plans

Some responses are activated only when specific events occur.

Example

Risk: Flooding at construction site.

Contingency Plan: Move operations to alternate location.

Once flooding occurs: Activate backup site.

4. Implement Opportunity Responses

Not all risks are negative.

Positive risks should also be implemented.

Example

Opportunity: Supplier offers faster delivery.

Response: Exploit opportunity and accelerate schedule.

5. Coordinate Risk Owners

Each risk should have an owner.

Risk owners:

6. Update Risk Information

New information may emerge.

Possible outcomes:

The risk register must be updated continuously.


Outputs

Change Requests

Implementation may reveal need for changes.

Examples:

Project Management Plan Updates

Risk response implementation may affect:

Project Documents Updates

Risk Register

Updated with:

Issue Log

Risks that occur become issues.


Risk Report

Provides: