Develop Budget is the process of aggregating estimated costs to establish an authorized cost baseline and determine project funding requirements.
Create a time-phased budget for the project
Establish a cost baseline for monitoring and control
Ensure funding is aligned with project needs and constraints
1. Cost Aggregation
Activity-level cost estimates are rolled up to:
Work package level (WBS)
Control accounts
Total project cost
Ensures the 100% scope is financially covered
Example:
Task costs → Module cost → Phase cost → Total project cost
2. Reserve Analysis
Determines additional funds for uncertainty:
Contingency reserves: For identified risks (included in baseline)
Management reserves: For unknown risks (outside baseline)
Ensures the budget is realistic and risk-adjusted
3. Historical Information
Uses past project data from Organizational Process Assets (OPA)
Helps validate estimates and improve accuracy
Example:
Previous solar project cost per MW used as a benchmark
4. Funding Limit Reconciliation
Aligns project spending with organizational funding constraints
If planned expenditure exceeds limits:
Adjust schedule (delay activities)
Re-sequence work
Reduce scope (if needed)
This ensures cash flow feasibility
5. Financing
Identifies how the project will be funded:
Internal funds
Loans
Equity or external investment
Considers:
Interest costs
Payment schedules
Financial risks
Important for large infrastructure projects
6. Cost Baseline
The approved, time-phased budget used for performance measurement
Includes:
All estimated costs
Contingency reserves
Excludes:
Management reserves
Forms the basis for tools like Earned Value Management (EVM)
7. Project Funding Requirements
Total funds needed, including:
Cost baseline
Management reserves
Defined as:
When funds are needed (cash flow)
How much is needed at each stage
Often represented as an S-curve (cash flow curve)
Outputs of Develop Budget
Cost Baseline
Project Funding Requirements
Updated Project Documents
Cost Estimates → Aggregate Costs → Add Reserves → Align with Funding Limits → Finalize Cost Baseline → Determine Funding Needs
Example (Solar Project)
Aggregated cost: ₹50 Cr
Contingency reserve: ₹5 Cr
Cost baseline: ₹55 Cr
Management reserve: ₹3 Cr
Total funding requirement = ₹58 Cr
If funding is limited to ₹20 Cr/year:
Schedule is adjusted to spread execution over 3 years
Budgeting is not just accounting—it’s about balancing cost, value, risk, and timing
Continuous review ensures alignment with changing project conditions
A time-phased budget is a project budget that is distributed across the project timeline, showing how much money is planned to be spent during specific time periods such as weeks, months, or quarters.
Instead of showing only the total project cost, it shows when the costs will occur.
A time-phased budget is the allocation of project costs over time to create the project’s cost baseline.
Suppose a project has a total budget of ₹12 lakh over 6 months.